If you work in Victorian construction, you've probably heard the term "SOPA" come up more than usual this year. That's because on 15 April 2026, the biggest shake-up of Victoria's Security of Payment Act in almost 20 years came into force, and it changes how almost everyone on a commercial job gets paid.
We speak with head contractors, subcontractors and site and commercial teams every day, so we've pulled together a plain-English rundown of what's changed, who it affects and what it means for the people doing the work.
The Building and Construction Industry Security of Payment Act 2002 (Vic), known as SOPA or the SOP Act, gives anyone doing construction work or supplying related goods and services a fast way to claim progress payments and resolve payment disputes through adjudication, without heading straight to court.
The problem was that Victoria's version was the odd one out nationally. It had a unique "excluded amounts" regime that kept many of the claims subbies most often fight over (disputed variations, latent conditions and delay costs) out of the fast-track process altogether. The 2025 reforms, introduced through the Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Act 2025 following a 2023 parliamentary inquiry, were designed to fix that and bring Victoria into line with states like NSW and WA.
1. "Excluded amounts" are gone. This is the headline change. Variations, latent conditions, time-related costs and changes in regulatory requirements can now be claimed and adjudicated under the Act. On the flip side, respondents can now deduct liquidated damages in their payment schedule where the contract allows it.
2. Payment terms are capped at 20 business days. A contract can no longer push payment out beyond 20 business days after a payment claim is served, and longer terms are void. If the contract says nothing, payment is due 10 business days after the earliest day a claim could be served.
3. Monthly claims replace "reference dates". Reference dates, long a source of technical disputes, have been removed. Claimants can now make one payment claim per calendar month (from the last day of the month) plus one on or after termination. A claim served too early is treated as served on the first valid day, rather than being invalid.
4. More time after practical completion. Claimants now have six months after practical completion to submit a payment claim for construction work, up from three months.
5. A proper Christmas shutdown. "Business days" under the Act no longer include 22 December to 10 January. No more adjudication applications landing on Christmas Eve with the clock ticking while everyone's on leave. Work done between 1 and 21 December can be claimed from 22 December, and work done from 22 to 31 December can be claimed from 31 January.
6. No new reasons at adjudication. If a head contractor or principal wants to dispute a claim, every reason needs to be in the payment schedule. New reasons can't be raised later in an adjudication response.
7. New rights around performance security. There's now a formal process to claim the release of retentions, bank guarantees and other performance security, and it can go to adjudication. A party must also give at least five business days' written notice before drawing on someone's security.
8. Unfair time bars can be struck out. Modelled on WA, a new section 13A lets an adjudicator, court, arbitrator or expert declare a notice-based time bar "unfair" where complying wasn't reasonably possible or was unreasonably onerous.
Yes, and this is the big one. The changes apply retrospectively to construction contracts already in place, not just those signed after 15 April. The main exception is that payment claims served, or adjudications lodged but not decided, before that date run under the old rules.
Worth noting: most domestic building contracts, and work carried out outside Victoria, still sit outside the SOP Act, according to the Building and Plumbing Commission.
Overall, it's good news for cash flow. Practically, it means:
The balance has shifted towards claimants, so contract administration needs to be tight:
From where we sit, the reforms put a premium on strong commercial and contract administration skills. With more claims now adjudicable and much less room for error in payment schedules, builders and subbies need people who can manage claims, variations, notices and deadlines properly, every month.
That means Contract Administrators, Commercial Managers, Quantity Surveyors and Project Managers who know the new rules are worth their weight in gold right now. And for candidates, getting across these changes is one of the easiest ways to stand out in your next interview.
Whether you're building out your commercial team or looking for your next role in Victorian construction, the team at 3D Recruitment can help. Get in touch with Paul Conway on the details below, or browse our current jobs.
This article is general information only and isn't legal advice. For advice on your specific contracts, speak with a construction lawyer